The San Diego commercial
building permit guide.

A commercial building permit in San Diego County comes from the building department of the city that has the address, or from the County for unincorporated areas. Most tenant improvements and remodels need one. The steps are the same everywhere: drawings, online submittal, plan review, corrections, issuance, inspections and a final sign-off.

Step zero

Which office has your address.

San Diego County has 19 building departments. The mailing address does not always tell you which one is yours.

Permit officeWorth knowing
City of San DiegoDevelopment Services DepartmentApplications are made online only. An interior office tenant improvement certified by a licensed architect can be issued the same day.
Unincorporated communitiesCounty of San Diego Planning & Development ServicesFallbrook, Ramona, Lakeside, Spring Valley and others. A mailing address that names a city can still be County land.
The other 17 citiesThat city's own building departmentCarlsbad, Chula Vista, Coronado, Del Mar, El Cajon, Encinitas, Escondido, Imperial Beach, La Mesa, Lemon Grove, National City, Oceanside, Poway, San Marcos, Santee, Solana Beach and Vista. Each has its own forms, fees and review times.

Scope

What needs a permit, and what usually does not.

The usual pattern for commercial interiors. The building department that has the address decides.

Usually needs a permitUsually does not
WallsNew, moved or removed walls.Furniture and movable partitions.
Ceilings and lightingNew ceilings, and new or moved light fixtures.Replacing ceiling tiles and lamps like for like.
PlumbingNew or moved sinks, restrooms and drains.Replacing a faucet or a toilet in the same place.
ElectricalNew circuits, panels and moved outlets.Plugging in equipment that uses an existing outlet.
Heating and coolingNew or moved units and ductwork.Filters and routine service.
FinishesFinishes that are part of permitted work.Paint, carpet, cabinets and countertops on their own.
UseChanging what the space is used for, even with no construction.A new tenant with the same use and no construction.

The process

Seven steps, the same in every city.

The forms and the fees change from one office to the next. The order does not.

  1. 01

    Drawings

    A plan of what is there and what will be built, with engineering where the work calls for it.

  2. 02

    Submittal

    The application, the drawings and the first fees go to the building department. Most now take them online.

  3. 03

    Plan review

    Reviewers check the drawings by discipline: building, fire, mechanical, electrical, plumbing and accessibility. Some projects add planning or health.

  4. 04

    Corrections

    The reviewers send comments. The drawings are revised and sent back. The number of rounds decides most of the time a permit takes.

  5. 05

    Issuance

    The remaining fees are paid, the contractor is named, and the permit is issued. Work can start.

  6. 06

    Inspections

    An inspector checks the work at set stages, before walls and ceilings are closed.

  7. 07

    Final sign-off

    The last inspection closes the permit. Where the use is new, a certificate of occupancy follows.

Other approvals

What runs beside the building permit.

A building permit is one approval. These are the others that commonly apply in San Diego County.

  • Health department

    The County's environmental health department reviews plans for restaurants and other food businesses.

  • Air district

    The San Diego County air district requires an asbestos survey before renovation or demolition, whatever the age of the building.

  • Fire

    Sprinkler and alarm changes, kitchen hood suppression and high storage racks carry fire permits of their own.

  • Historical review

    In the City of San Diego, a permit on a parcel with a structure 45 years old or older can bring a historical review.

  • The landlord

    Most leases require the landlord to approve the drawings before they go to the city.

  • The coast

    Near the coast, changes to the outside of a building can need a coastal permit.

What we do about it

Six things that speed a permit up.

None of them is a shortcut. Each one removes a round of waiting.

  1. 01

    A complete first submittal

    Most delays start with a missing sheet or form. The reviewer's checklist is public, so the set is built to it.

  2. 02

    One round of answers

    Every comment answered at once, in writing, with the changed sheets marked.

  3. 03

    Settle the use first

    Whether the project changes the use of the space decides which rules apply. It is asked before the drawings start.

  4. 04

    Use the fast lane

    Where a city offers same-day or over-the-counter review for small work, the project is shaped to qualify.

  5. 05

    Start the other approvals early

    Health, fire and landlord reviews run at the same time as plan review, not after it.

  6. 06

    Order during review

    Equipment and materials with long lead times are ordered while the permit is in review.

Questions

Permit questions.

Do I need a permit for a tenant improvement in San Diego?

Almost always. New or moved walls, ceilings, lighting, plumbing, electrical circuits and air conditioning all need permits. Paint, carpet and cabinets usually do not. A change in what the space is used for can need a permit even when nothing is built.

How long does a commercial building permit take in San Diego?

It depends on the size of the job, the city, and the number of correction rounds. In the City of San Diego, an interior office tenant improvement certified by a licensed architect can be issued the same day. Projects with several reviewers take longer, and every round of corrections adds to it. Each building department publishes its current review times.

What is a certificate of occupancy?

A certificate of occupancy is the building department's written statement that a space may be used for a stated purpose, such as an office, a store or a restaurant. It follows the final inspection. A new building needs one, and so does a space whose use is changing.

Who applies for the permit, the tenant or the contractor?

The owner, a tenant with the owner's authorization, or a licensed contractor can apply. On our projects we apply, answer the plan check comments and schedule the inspections.

What happens if work was done without a permit?

The city can stop the work and require drawings and a permit after the fact, and finished walls or ceilings may have to be opened so an inspector can see inside. Unpermitted work also tends to surface when a building is sold or a new tenant applies for a permit.

Start here

Request a site walk in San Diego County.

Tell us about the space. We will call to set a time to walk it with you.

Office12396 World Trade Dr, Suite 106A
San Diego, CA 92128

Phone(858) 371-3839

HoursMonday to Friday, 8:00 AM to 4:30 PM

By providing your number and clicking “Request a site walk”, you agree to be contacted by Kaminskiy Commercial Construction about your project via phone, email, and text messages, including marketing messages about special offers, discounts, and promotions. Consent is not a condition of purchase. Message and data rates may apply. You can unsubscribe at any time by replying STOP. For help, reply HELP. Message frequency will vary.